December 2023: Final plat submitted
February 6th, 2024: Final plat approved by City Council
March 2024: Construction expected to begin
March 23rd, 2024: Removals and tree clearing began
March 28th, 2024: Equipment placed on-site
Proposed construction schedule (weather dependent and subject to change):
- March through May: Bring in equipment/Removals and grading
- June through August: Utility installation
- August through October: Street construction
The development of the first phase is expected to be completed mid 2025.