May 2025: At the recommendation of the Park & Recreation Commission, City Council authorized staff to solicit quotes for the Sculpture/Riverway Park improvements
August 2025: City staff reviewed quotes and awarded Sunram Construction Inc., with minor adjustments to their proposal to reduce overall cost
September 2025: Work begins in park
Oct. 17, 2025: The contractor has completed their portion of the project
Oct. 20, 2025: Public Works staff will begin prepping the remaining paths for aggregate placement (estimate approximately 2 weeks to complete)
End of October/Early November 2025: Work is expected to be complete - please note that timelines may change due to weather